Testing of electric motors
With the electric motor roller dynamometer maps can be drawn of the electric machine efficiency, i.e. charts of the electric motor efficiency as a function of the speed and load (torque).
Testing capabilities
Mechanical
parameters of electric motors which we can test:
- torque meter No. 1:
- maximum torque 100 Nm,
- maximum speed 12,000 rpm,
- maximum mechanical power 125.67 kW;
- torque meter No. 2:
- maximum torque 500 Nm,
- maximum speed 7,000 rpm,
- maximum mechanical power 366.5 kW;
- future torque meter:
- maximum 1,000 Nm,
- maximum speed 7,000 rpm,
- maximum mechanical power 650 kW;
- approximate maximum motor dimensions: a cylinder of 52 cm in length and 32 cm in diameter (it is possible to modify motor mounts and frames for larger motors).
Testing of electric motors – parameters of
L-ILOT inverters
Electrical
parameters of electric motors that we can handle with our inverters:
- Inverter No. 1:
- rated current 200 A,
- peak current 400 A (60 sec.),
- maximum supply voltage 700 V DC;
- Inverter No. 2:
- rated current 700 A,
- peak current 800 A (60 sec.),
- maximum supply voltage 450 V DC.
Electric motors tests – stand
The stand
is equipped with a battery simulator with the following main parameters:
- simulator power supply 3×400 V AC,
- continuous power 80 kW,
- instantaneous power 120 kW (60 sec.),
- adjustable output voltage 24-800 V DC,
- rated current +/- (bi-directional) 267 A,
- peak current +/- (bi-directional) 400 A,
- the ability to quickly prototype the required energy storage capacity and conduct long-term tests with DC voltage.
Liquid cooling of motors/inverters
- water cooler No. 1 – maximum heat capacity 5 kW;
- water cooler No. 2 – maximum heat capacity 10 kW.
Testing of electric motors – possibility to conduct tests with the customer’s inverters:
- the electric power of a single inverter powered directly from the DC bus in the configuration of electric motor + generator as a load must not exceed 380 kW;
- the electric power of a single inverter supplied directly from the 3×400 V AC network with the configuration of an electric motor + generator as a load must not exceed 650 kW.